Work Session
1250 Union Road Work Session
West Seneca, NY 14224 July 10, 2017
Supervisor Sheila M. Meegan called the work session to order at 3:00 P.M. with the Pledge of Allegiance led by Steven Tanner.
ROLL CALL: Present - Sheila M. Meegan Supervisor
William P. Hanley, Jr. Councilman
John Fenz Town Attorney
Amy Kobler Deputy Town Clerk
Matthew English Highway Sup’t.
John Gullo Senior Code Enforcement Officer
Daniel Denz Police Chief
Steven Tanner Town Engineer
Lauren Masset Recreation Supervisor
Laura Devine Human Resources
Emily Melski Secretary to Supervisor
Supervisor Meegan read the Fire Prevention Code instructing the public where to exit in case of a fire or an emergency.
RECREATION SUPERVISOR LAUREN MASSET
- Summer programs are underway and running well
- Currently working on finalizing the dates and movie selection for the “Movie in the Park” event
EMILY MELSKI - FARMERS MARKET
- Kids Day will be held July 20th with the Recreation Department organizing games, face painting, etc.
- Lions Club will host Celebrate Summer on July 27th
HIGHWAY DEPARTMENT
- Agenda items - two employees resigned to take different employment
- Milling and paving will begin Monday, July 17th on Thorndale Avenue, Tindle Avenue and Bellwood Avenue and should be completed in approximately three weeks
SENIOR CODE ENFORCEMENT OFFICER JOHN GULLO
- Working on finalizing sign ordinance amendments with the biggest change being seen along the Union Road corridor; signs on trailers will not be permitted
TOWN ENGINEER STEVEN TANNER
- Community Center & Library Project – on schedule overall
ü
Controls will be bought off state bid; same control system the town is used to
ü
Demo on existing part of library began; small amount of asbestos tile that needs to be abated
ü
Road closest to the library will stay closed and signage will be put up for parking at the temporary library
WEST SENECA TOWN OFFICES TOWN BOARD PROCEEDINGS
1250 Union Road Work Session
West Seneca, NY 14224 July 10, 2017
Page two . . .
- Basement inspections continue in phase 3; will be going to phase 4 in approximately three weeks
- Final walk through of Rosewood Project; project is at completion with only minor things necessary to finish
SUPERVISOR MEEGAN
Assemblyman Michael Kearns was able to obtain funds through a grant for library project upgrades
Covington Drive area will be added to the sound barrier request resolution
Part-time clerical positions are available
TOWN ATTORNEY JOHN FENZ
Public hearing date to be set for July 24th for Sign Ordinance amendments
HUMAN RESOURCES LAURA DEVINE
- Summer hiring process is complete and all went well
EXECUTIVE SESSION
Motion by Supervisor Meegan, seconded by Councilman Hanley, to recess to executive session at 3:20 P.M. to discuss a litigation matter.
Ayes: All Noes: None Motion Carried
The board members returned from executive session at 5:00 P.M. and the work session concluded.
_______________________________________
JACQUELINE A FELSER, TOWN CLERK
July 10, 2017, 3:00 pm